Pictures during 2006 restaurant building works |
|
![]() ![]() ![]() |
|
Nov 12th 2006 | Nov 17th 2006 - prior to opening |
![]() |
|
The Minstrels Gallery - Nov 17th 2006 - prior to opening | |
![]() |
![]() |
The Minstrel | |
![]() |
|
![]() |
![]() |
All above - Nov 17th 2006 - prior to opening on Nov 18th 2006 | |
Now see progress of building works which began Aug 14th 2006 ..... | |
![]() |
|
August 20th 2006 - clearing & preparations for footings started August 14th | |
![]() |
|
Aug 27th 2006 - 1st signs ! | |
![]() ![]() |
|
September 3rd 2006 - the concrete base | |
![]() ![]() |
|
September 10th 2006 - taking shape | |
![]() |
|
September 17th - walls are up | |
![]() ![]() |
|
September 24th - roof members in place | |
![]() ![]() |
|
October 15th - only four weeks to go ! | |
![]() ![]() |
|
Walls plasterd & heating in | |
![]() ![]() |
|
The new entrance ..... and patio doors | |
![]() ![]() |
|
November 12th 2006 - nearly there ! | |